Reconstruction of the reservoir
Obukhiv

   Reconstruction of the existing sludge tank by increasing its height. The work was carried out in cramped conditions in a short time during the short-term annual shutdown of the plant. The slurry mixer shaft was also dismantled, lengthened and mounted back.

    In addition, were installed about 700 m of technological pipelines with diameters of up to 114 mm with supporting metal structures (steam pipe, condensate pipe, technical water, hot water supply, air pipe, slurry pipe)

2019